Good-hearted managers don’t like asking for status. It’s awkward, feels like nagging, and gets even worse when they have to ask follow-up questions to get sufficiently clear about what’s going on.
Managers would rather be able to see the status themselves whenever they need to. We saw in the last chapter how organizing to-dos into scopes helps the team to stay on top of the work. But this doesn’t help the manager directly. There are a couple problems with to-dos that make them insufficient for judging status.
The tasks that aren’t there
Consider a list with a few completed items and no incomplete items left. This could mean that all the work is done. But it could also mean that the team knows there’s more work but hasn’t defined tasks yet.
Sometimes a team will define a scope
early in the project without populating it with tasks. It marks that some work needs to be done but that actual tasks haven’t been discovered yet.
Or think about doing some QA at the end of a scope. All the tasks are done. There’s nothing else to do. Then the act of testing populates the scope with new tasks for the issues found.
This goes back to the notion of imagined
versus discovered
tasks. In our naive notion of a list that’s planned up-front, somebody populates it with items that are gradually checked off. In real life, issues are discovered by getting involved in the problem. That means to-do lists actually grow as the team makes progress.
If we tried to judge at t2 how far along the project is, we’d be misled. From an outsider’s perspective, there’s no way to know whether the number of outstanding tasks will go down or up. To know that, you’d need more context on the work inside the scope to understand what it means that those particular tasks are done and whether others might still be coming.
Estimates don’t show uncertainty
Some teams try to attach estimates to their tasks or scopes to report status. The problem with estimates is they have a very different meaning depending on the nature of the work being estimated.
Say you have two tasks, both estimated to take four hours. If one task is something the team has done ten times in the past, you can be confident in the estimate. Suppose the other task is something the team has never done before, or it has unclear interdependencies. It could take the four hours if all goes perfectly, but due to the unknowns in it, it could stretch out to two to three days. It’s not meaningful to write “4 hours, or maybe 3 days” as the estimate.
Recognizing this, we came up with a way to see the status of the project without counting tasks and without numerical estimates. We do that by shifting the focus from what’s done or not done to what’s unknown and what’s solved. To enable this shift, we use the metaphor of the hill.
Work is like a hill
Every piece of work has two phases. First there’s the uphill phase of figuring out what our approach is and what we’re going to do. Then, once we can see all the work involved, there’s the downhill phase of execution.
Let’s use an everyday example to get the feeling of the hill.
Suppose you’re planning to host a dinner party. You’ve set the date, but it’s still a couple weeks ahead and you haven’t thought about what to cook yet. You have no idea what type of cuisine the meal will be or what dish to make. That would place you at the start of the hill on the bottom-left.
Next you think about who’s attending and note that a couple people are vegetarian. That eliminates some options (like grilling out) but still leaves a lot of options open. You consider both Italian and Indian. You think Indian might be more fun to cook, with more interesting vegetarian options. So you decide to look for Indian recipes.
At this point, the question “What percent complete is the project?” doesn’t even make sense. And if someone asked you to estimate how long the shopping and prep will take, you couldn’t answer that either because you haven’t chosen a dish yet. The answer would be: “I’ve done some work to figure out what kind of cuisine, but I haven’t narrowed it down to a specific dish yet.” We can represent that by putting you halfway up the “figuring it out” side of the hill.
Next you do some searching online and look through your recipe books. You want to find a recipe that will be interesting but doesn’t require ingredients that will be too hard to find. You settle on a recipe and prepare a shopping list.
Now you are in a very different position than before. The feeling changes from “I’m still not sure what I’m doing” to “Now I know what to do.” You’re at the top of the hill.
From this vantage point, you can see all of the steps that are left. It’s even fair to estimate how long all the work will take (“Let’s see…an hour to grocery shop, 30 minutes of prep, cook for 45 minutes…”).
The day before the dinner party, you go to the grocery store and buy the ingredients. This moves you downhill. You’re closer to finishing the task.
Next comes the work of prepping and cooking the meal.
After the meal is over, there’s just a little work left: the clean-up.
Note how the hill shows how the work feels at different stages. The uphill phase is full of uncertainty, unknowns, and problem solving. The downhill phase is marked by certainty, confidence, seeing everything, and knowing what to do.
Scopes on the hill
We can combine the hill with the concept of scopes from the last chapter. The scopes give us the language for the project (“Locate,”